isCriticalTask
信息
此功能仅在 PRO 版中可用。
Description
检查指定任务是否为关键任务
isCriticalTask: (task: Task) => boolean
Parameters
task- (required) Task - 任务对象
Returns
value- (boolean) - 'true' 表示指定的任务是关键任务, 'false' 表示否则
Example
const tasks = {
data:[
{id:1, text:"Project #1", start_date:"01-04-2023", duration:18, type:"project"},
{id:2, text:"Task #1", start_date:"02-04-2023", duration:8, parent:1},
{id:3, text:"Task #2", start_date:"13-04-2023", duration:8, parent:1}
],
links:[
{id:1, source:1, target:2, type:"1"},
{id:2, source:2, target:3, type:"0"}
]
};
gantt.config.highlight_critical_path = true; /*!*/
gantt.init("gantt_here");
gantt.parse(tasks);
gantt.isCriticalTask(gantt.getTask(2));// ->'false' /*!*/
gantt.isCriticalTask(gantt.getTask(3));// ->'true' /*!*/
Related samples
Details
注释
此方法在 critical_path 扩展中定义,因此您需 要激活 critical_path 插件。请在 Critical Path 文章中阅读详细信息。