getResourceAssignments
信息
该功能仅包含在PRO版本中。
Description
返回指定资源关联的所有任务
getResourceAssignments: (resourceId: string | number, taskId?: string | number) => ResourceAssignment[]
Parameters
resourceId- (required) string | number - 资源的标识符taskId- (optional) string | number - 任务的标识符
Returns
assignments- (ResourceAssignment[]) - 表示分配给资源的任务对象数组
Example
gantt.getResourceAssignments("6"); // -> 显示详情
Related samples
Details
此方法返回一个对象数组,结构如下:
[
{task_id: 5, resource_id: "6", value: 5, delay: 0, duration: 7,
start_date: "03-04-2019 00:00", end_date: "12-04-2019 00:00",
id: 1617258553240, mode: "default"},
{task_id: 18, resource_id: "6", value: 2, delay: 0, duration: 2,
start_date: "05-04-2019 00:00", end_date: "09-04-2019 00:00",
id: 1617258553250, mode: "default"},
{task_id: 19, resource_id: "6", value: 3, delay: 0, duration: 4,
start_date: "09-04-2019 00:00", end_date: "13-04-2019 00:00",
id: 1617258553251, mode: "default"},
{task_id: 21, resource_id: "6", value: 5, delay: 0, duration: 4,
start_date: "03-04-2019 00:00", end_date: "09-04-2019 00:00",
id: 1617258553254, mode: "default"}
]
每个对象包含以下属性:
- id - (string | number) - 分配的唯一标识符
- task_id - (string | number) - 分配给资源的任务ID
- resource_id - (string | number) - 分配给任务的资源ID
- value - (number | string) - 分配给任务的资源数量
- delay - (number) - 分配开始日期与任务开始日期之间的偏移量
- start_date - (Date) - 分配计划开始时间
- end_date - (Date) - 分配计划结束时间
- duration - (number) - 分配持续时间
- mode - (string) - 计算资源分配时间的模式: "default"|"fixedDates"|"fixedDuration"
- [customProperty: string] - (any) - 任何额外的自定义属性
注释
note 属性 delay, duration, start_date, end_date, id 和 mode 仅在启用 process_resource_assignments 时自动填充。
Related API
Related Guides
Change log
- 从v7.1开始,返回的对象包含 delay, duration, start_date, end_date, id 和 mode 属性