본문으로 건너뛰기

getTaskWork

Description​

Returns a task's work in the configured effort work unit

getTaskWork: (taskId: string | number) => number;

Parameters​

  • taskId is the ID of an existing task.

Returns​

The amount of work in the configured work unit. When effort calculations are enabled, a summary task returns the total work of its children. For other tasks, the method returns stored work if available. When there is no stored value, Gantt derives work from the task dates and allocations if effort calculations are enabled, or returns 0 if they are disabled.

Example​

const work = gantt.getTaskWork(1);

Change log​

  • Added in v10.1.
Need help?
Got a question about the documentation? Reach out to our technical support team for help and guidance. For custom component solutions, visit the Services page.