getResourceAssignments

返回指定资源关联的所有任务

ResourceAssignment[] getResourceAssignments(string|number resourceId, [string|number taskId] );
resourceIdstring|number资源的标识符
taskIdstring|number任务的标识符
ResourceAssignment[]表示分配给资源的任务对象数组

Available only in PRO Edition

Example

gantt.getResourceAssignments("6"); // -> 显示详情

Related samples

Details

该功能仅包含在PRO版本中。

此方法返回一个对象数组,结构如下:

[ 
    {task_id: 5, resource_id: "6", value: 5, delay: 0, duration: 7, 
        start_date: "03-04-2019 00:00", end_date: "12-04-2019 00:00", 
        id: 1617258553240, mode: "default"},
    {task_id: 18, resource_id: "6", value: 2, delay: 0, duration: 2, 
        start_date: "05-04-2019 00:00", end_date: "09-04-2019 00:00", 
        id: 1617258553250, mode: "default"},
    {task_id: 19, resource_id: "6", value: 3, delay: 0, duration: 4, 
        start_date: "09-04-2019 00:00", end_date: "13-04-2019 00:00", 
        id: 1617258553251, mode: "default"},
    {task_id: 21, resource_id: "6", value: 5, delay: 0, duration: 4, 
        start_date: "03-04-2019 00:00", end_date: "09-04-2019 00:00", 
        id: 1617258553254, mode: "default"}
]

每个对象包含以下属性:

  • id - (string | number) - 分配的唯一标识符
  • task_id - (string | number) - 分配给资源的任务ID
  • resource_id - (string | number) - 分配给任务的资源ID
  • value - (number | string) - 分配给任务的资源数量
  • delay - (number) - 分配开始日期与任务开始日期之间的偏移量
  • start_date - (Date) - 分配计划开始时间
  • end_date - (Date) - 分配计划结束时间
  • duration - (number) - 分配持续时间
  • mode - (string) - 计算资源分配时间的模式: "default"|"fixedDates"|"fixedDuration"
  • [customProperty: string] - (any) - 任何额外的自定义属性

属性 delay, duration, start_date, end_date, idmode 仅在启用 process_resource_assignments 时自动填充。

See also
Change log

从v7.1开始,返回的对象包含 delay, duration, start_date, end_date, idmode 属性