Description​

Converts an XML or MPP MS Project file to JSON

importFromMSProject: (config: any) => void

Parameters​

  • config - (required) object - an object with configuration properties of an imported file

Example​

gantt.importFromMSProject({
data: file,
taskProperties: ["Notes", "Name"],
callback: function (project) {
if (project) {
gantt.clearAll();
if (project.config.duration_unit) {
gantt.config.duration_unit = project.config.duration_unit;
}
gantt.parse(project.data);
}
}
});

Details​

note

The method requires HTML5 File API support.

note

This method is defined in the export extension, so you need to activate the export_api plugin. Read the details in the Export and Import from MS Project article.

note

If you use the Gantt version older than 8.0, you need to include the https://export.dhtmlx.com/gantt/api.js on your page to enable the online export service, e.g.:

<script src="codebase/dhtmlxgantt.js"></script>
<script src="https://export.dhtmlx.com/gantt/api.js"></script>

The method takes as a parameter an object with configuration properties of an imported file:

  • data - an instance of File which should contain either MPP or XML Project file.
  • callback - a callback function.
  • durationUnit - sets an expected duration unit ("minute", "hour", "day", "week", "month", "year").
  • projectProperties - specifies an array of project properties that should be put into the response.
  • taskProperties - specifies an array of additional task properties to be imported.
  • assignmentProperties - specifies an array of additional resource assignment properties to be imported, or the "populated" string to import all assignment properties that have values. The parameter is added in v10.0.4 and requires version 2.5.0.0 or later of the export module.

Check the detailed descriptions of the import settings in the related section.

Response​

The response will contain a JSON of the following structure:

{
data: {},
config: {},
resources: [],
worktime: {},
calendars: []
}
  • data - (object) a gantt data object. Each task has the following properties: id, open, parent, progress, start_date, text, resource. Dates are stringified in the "%Y-%m-%d %H:%i" format.
  • config - (object) a gantt configuration object with settings retrieved from the project file.
  • resources - (array) an array of objects (each having the following properties: {id: string, name: string, type: string, calendar: string} that represent the list of resources from the project file.
  • worktime - (object) an object containing the working time settings from the project calendar. It can contain the following attributes:
    • id - (string | number) optional, the calendar id
    • hours - (array) an array with global working hours, sets the start and end hours of the task
    • dates - (array) an array of dates that can contain:
      • 7 days of the week (from 0 - Sunday, to 6 - Saturday), where 1/true stands for a working day and 0/false - a non-working day
      • other records are dates
  • calendars - (array) an array containing calendar configuration objects for creating a new calendar.
    • calendarConfig - (object) a calendar configuration object that can contain the following attributes:
      • id - (string | number) optional, the calendar id
      • name - (string) the calendar name
      • hours - (array) an array with global working hours, sets the start and end hours of the task
      • dates - (array) an array of dates that can contain:
        • 7 days of the week (from 0 - Sunday, to 6 - Saturday), where 1/true stands for a working day and 0/false - a non-working day
        • other records are dates