Skip to main content

dhtmlxGantt with Svelte

You should be familiar with the basic concepts and patterns of Svelte to use this documentation. If you are not, please refer to the Svelte documentation for a getting-started tutorial.

DHTMLX Gantt is compatible with Svelte. You can check the corresponding example on GitHub: DHTMLX Gantt with Svelte Demo.

Creating a project​

Before you start to create a new project, install Vite (optional) and Node.js.

To create a Svelte project, we will use Svelte with Vite and run the following command:

npm create vite@latest

Check the details in the related article.

Installation of dependencies​

Next you should go to the app directory. Let's name our project gantt-svelte and choose the svelte option, then run:

cd gantt-svelte

After that you should install dependencies and run the app. For this, you need to make use of a package manager:

  • if you use yarn, you need to call the following commands:
yarn install
yarn dev
  • if you use npm, you need to call the following commands:
npm install
npm run dev

You should now have your Svelte project running on http://localhost:5173.

Gantt Svelte app running

Creating Gantt​

Now we should get the DHTMLX Gantt code. Firstly, we need to stop the app by pressing Ctrl+C in the command line. Then we can proceed with installing the Gantt package.

Step 1. Package installation​

The PRO versions of the library are available for the npm/yarn install from our private repository, please follow this instruction to gain access to it.

After you've got the Evaluation version of the Gantt, you can install it with the following commands:

  • for npm:
npm install @dhx/trial-gantt
  • for yarn:
yarn add @dhx/trial-gantt

Alternatively, since the zip-package of the library is structured as an npm module, you can install it from a local folder.

Step 2. Component creation​

Now we should create a Svelte component, to add a Gantt into the application. Let's create a new file in the src/ directory and name it Gantt.svelte.

Importing source files​

Open the newly created Gantt.svelte file and import Gantt source files. Note that:

  • if you've installed the Gantt package from a local folder, your import paths will look like this:
Gantt.svelte
import { Gantt} from "dhtmlx-gantt";
import "dhtmlx-gantt/codebase/dhtmlxgantt.css";
  • if you've chosen to install the trial version, the import paths should be as in:
Gantt.svelte
import { Gantt} from "@dhx/trial-gantt";
import "@dhx/trial-gantt/codebase/dhtmlxgantt.css";

In this tutorial we will use the trial version of Gantt.

Setting the container and adding Gantt​

To display Gantt on the page, we need to set the container to render the component inside. Check the code below:

Gantt.svelte
<script>
import "@dhx/trial-gantt/codebase/dhtmlxgantt.css";
import { onMount } from "svelte";
import { Gantt } from "@dhx/trial-gantt";

let container;
onMount(() => {
let gantt = Gantt.getGanttInstance();
gantt.init(container);

return () => {
gantt.destructor();
};
});
</script>

<div bind:this="{container}" style="width: 100%; height: 100%;"></div>

To make the Gantt container occupy the entire space of the body, you need to remove the default styles from the app.css file located in the src/ folder and add the following one:

src/app.css
body, #app {
margin: 0;
padding: 0;
height: 100vh;
width: 100%;
}

Step 3. Adding Gantt into the app​

Now it's time to add the component into our app. Open src/App.svelte and use the Gantt component instead of the default content by inserting the code below:

src/App.svelte
<script>
import Gantt from "./Gantt.svelte";
</script>

<Gantt/>

After that, when we start the app, we should see an empty Gantt on a page:

Gantt Svelte init

Step 4. Providing Data​

To add data into the Gantt, we need to provide a data set. Let's create the data.js file in the src/ directory and add some data into it:

src/data.js
export function getData() {
const tasks = {
data: [
{
id: "10",
text: "Project #1",
start_date: "01-04-2025",
duration: 3,
order: 10,
progress: 0.4,
open: true,
},
{
id: "1",
text: "Task #1",
start_date: "01-04-2025",
duration: 1,
order: 10,
progress: 0.6,
parent: "10",
},
{
id: "2",
text: "Task #2",
start_date: "02-04-2025",
duration: 2,
order: 20,
progress: 0.6,
parent: "10",
},
],
links: [{ id: 1, source: 1, target: 2, type: "0" }],
};
return tasks;
}

We should pass props (our data) to the Gantt component in the App.svelte file:

App.svelte
<script>
import Gantt from "./Gantt.svelte";
import { getData } from "./data.js";
</script>

<Gantt tasks="{getData()}" />

And use the props in the gantt.parse() method in the Gantt component:

Gantt.svelte
<script>
import "@dhx/trial-gantt/codebase/dhtmlxgantt.css";
import { onMount } from "svelte";
import { Gantt } from "@dhx/trial-gantt";

export let tasks;

let container;
onMount(() => {
let gantt = Gantt.getGanttInstance();
gantt.init(container);
gantt.parse(tasks);

return () => {
gantt.destructor();
};
});
</script>

<div bind:this="{container}" style="width: 100%; height: 100%;"></div>

Now, if you reopen the app page, you should see a Gantt with tasks:

Gantt tasks

Step 5. Saving Data​

To capture changes made in the Gantt, you can use a dataProcessor handler that lets you "communicate" with the server-side backend. The handler can be declared either as a function or as a router object. dhtmlxGantt accepts a Promise response from the handler, so your Gantt will correctly process the completion of an action.

You can create a DataProcessor via the createDataProcessor() API method and capture changes like this:

gantt.createDataProcessor(function(entity, action, data, id) {​
gantt.message(`${​entity} ${​action}`);
});

If your service changes the task id after creating a new record (which it usually does), make sure that your Promise returns an object with (id: databaseId) or (tid: databaseId) as a result, so that Gantt could apply the new database id to the record. Get more information about the server side.

Well, Svelte Gantt is ready, you are welcome to check out the full demo on GitHub.

XSS, CSRF and SQL Injection Attacks​

Pay attention that Gantt doesn't provide any means of preventing an application from various threats, such as SQL injections or XSS and CSRF attacks. It is important that responsibility for keeping an application safe is on the developers implementing the backend.

Check the Application Security article to learn the most vulnerable points of the component and the measures you can take to improve the safety of your application.

Need help?