checks whether the specified task is critical
task | Task | the task's object |
boolean | 'true' if the specified task is critical, 'false' otherwise |
Available only in PRO Edition
const tasks = {
data:[
{id:1, text:"Project #1", start_date:"01-04-2023", duration:18, type:"project"},
{id:2, text:"Task #1", start_date:"02-04-2023", duration:8, parent:1},
{id:3, text:"Task #2", start_date:"13-04-2023", duration:8, parent:1}
],
links:[
{id:1, source:1, target:2, type:"1"},
{id:2, source:2, target:3, type:"0"}
]
};
gantt.config.highlight_critical_path = true; gantt.init("gantt_here");
gantt.parse(tasks);
gantt.isCriticalTask(gantt.getTask(2));// ->'false' gantt.isCriticalTask(gantt.getTask(3));// ->'true'
This functionality is available in the PRO edition only.
This method is defined in the critical_path extension, so you need to activate the critical_path plugin. Read the details in the Critical Path article.