checks how much time (in the current duration unit) a task has before it starts to affect other tasks
The method is deprecated.
task1 | object | the object of the 1st task to check the slack for |
task2 | object | the object of the 2nd task to check the slack for |
number|string | a slack between tasks in the current duration units or 'Infinity', if tasks are not linked |
Available only in PRO Edition
const tasks = {
data:[
{id:1, text:"Project #1", start_date:"01-04-2013", duration:18, type:"project"},
{id:2, text:"Task #1", start_date:"02-04-2013",duration:8, parent:1},
{id:3, text:"Task #2", start_date:"13-04-2013",duration:8, parent:1}
],
links:[
{id:1, source:1, target:2, type:"1"},
{id:2, source:2, target:3, type:"0"}
]
};
gantt.config.highlight_critical_path = true;
gantt.init("gantt_here");
gantt.parse(tasks);
gantt.getSlack(gantt.getTask(2), gantt.getTask(3)); // -> 1
The getSlack method is deprecated. Use the following methods to get free/total slack of a task:
gantt.getFreeSlack(task);
gantt.getTotalSlack(task);
The getSlack method is available in the PRO edition only.
This method is defined in the critical_path extension, so you need to include it on the page. Read the details in the Critical Path article.