Critical Path

This functionality is available only in the PRO edition

A critical path is a sequence of tasks that can't be delayed. Otherwise, the whole project would be delayed.
The critical path also determines the shortest time the project can take.

A task is considered critical if it has no days of slack and any delay would directly affect the project completion date.
Slack time is the time that a task can slip without affecting other tasks or the project's completion date.

To start using the extension, include the ext/dhtmlxgantt_critical_path.js file on the page.

To show the critical path in the Gantt chart, set the highlight_critical_path property to 'true':

Making the Gantt chart to display the critical path

<!DOCTYPE html>
<html>
<head>
   <script src="codebase/dhtmlxgantt.js"></script>   
   <link href="codebase/dhtmlxgantt.css" rel="stylesheet">   
   <script src="codebase/ext/dhtmlxgantt_critical_path.js"></script>  </head>
<body>
    gantt.config.highlight_critical_path = true;
    //your code will be here
</body>
</html>

Related sample:  Critical path

Note that when the property is enabled, dhtmlxGantt will automatically check the status of tasks and update the critical path. Critical tasks and links will have additional 'critical_task' and 'critical_link' CSS classes, respectively.

Each time a task is modified, dhtmlxGantt will completely re-draw data in order to re-calculate the critical path. Sometimes it may create performance issues. For that case, the component provides public methods that allow you to check a certain task or link and implement a performance-friendlier strategy for displaying a critical path.

Checking if a task is critical

To check if some task is critical, use the isCriticalTask method:

gantt.config.highlight_critical_path = true; gantt.init("gantt_here");
gantt.parse(tasks);
 
gantt.isCriticalTask(gantt.getTask("task3"));// ->'true'

Related sample:  Critical path

Checking if a link is critical

To check if a link is critical (connects 2 critical tasks), use the isCriticalLink method:

gantt.isCriticalLink(gantt.getLink("link1"));

Related sample:  Critical path

Getting free and total slack

Free slack - a period of time that can be used to increase the duration of a task or move it on the timeline without affecting the next task it is connected with.

To get the free slack of a task, make use of the getFreeSlack method. It takes the object of a task as a parameter:

var task = gantt.getTask(7);
gantt.getFreeSlack(task);

Related sample:  Show Slack time

Total slack - a period of time that can be used to increase the duration of a task or move it on the timeline without affecting the time of ending of the whole project.

To get the total slack of a task, make use of the getTotalSlack method. It takes the object of a task as a parameter as well:

var task = gantt.getTask(7);
gantt.getTotalSlack(task);

Related sample:  Show Slack time

Slack

Customizing the critical path behaviour

By default, the gantt applies the default behavior to a critical path, such as default style for highlighting, re-calculating the critical path with each data update.

To manipulate the visibility of the critical path, use the following approach:

var isEnabled = false
function updateCriticalPath(){
    isEnabled = !isEnabled;
 
    gantt.config.highlight_critical_path = isEnabled;
 
    gantt.render();
}

It can be useful when you have a big number of tasks and re-calculating the critical path may affect the performance.

To manually re-calculate the critical path and apply the related styling, use the following approach:

gantt.templates.task_class = function(start, end, task){
    if(gantt.isCriticalTask(task))
        return "critical_task";
      return "";
};
 
gantt.templates.link_class = function(link){
    if(gantt.isCriticalLink(link))
        return "critical_link";
      return "";
};
 
var tasks = {
    data: [
        { "id": 1, "text": "Office itinerancy", open:true, type:"project" },
        { "id": 2, "text": "Office facing", "start_date": "21-07-2014", 
            "duration": "20", "parent": "1" },
        { "id": 3, "text": "Furniture installation", "start_date": "21-07-2014", 
            "duration": "5", "parent": "1" },
        { "id": 4, "text": "The employee relocation", "start_date": "28-07-2014", 
            "duration": "15", "parent": "1" },
        { "id": 5, "text": "Interior office", "start_date": "28-07-2014", 
            "duration": "15", "parent": "1" }
    ],
    links: [
        { id: "1", source: "2", target: "3", type: "0" },
        { id: "2", source: "3", target: "4", type: "0" },
        { id: "3", source: "4", target: "5", type: "0" }
    ]
};
gantt.init("gantt_here");
 
gantt.parse(tasks);

Setting lag and lead times between tasks

It's possible to set lag and lead times between tasks of the critical path. You find the details here.