Manually Scheduled Summary Tasks

There is a possibility to schedule projects (summary tasks) manually. This feature serves to increase flexibility and accuracy in managing projects with Gantt charts.

By default, summary tasks automatically calculate their dates based on the earliest start and latest end dates of their subtasks. You can also set fixed start and end dates for summary tasks independently of their subtasks. As a result, the Gantt chart will display both the fixed duration and the duration derived from subtasks.

Related sample:  Manually Scheduled Projects

To activate this feature for a summary task, set the auto_scheduling property to false.

The fixed dates are stored in task.start_date and task.end_date, while the computed dates from subtasks are available in task.$auto_start_date and task.$auto_end_date.

gantt.parse({
  data: [
    {
      id: 1,
      text: "Project Phase 1",
      type: "project",
      start_date: "2025-05-01 00:00:00",
      duration: 15,
      auto_scheduling: false /* ! */
    },
    // ...
  ],
});

Both the fixed duration of the summary task and the actual duration calculated from its subtasks are displayed in the Gantt chart.

If the subtask date range falls outside the assigned dates of the summary task, the summary task will be highlighted to indicate a scheduling conflict. This visual cue helps end-users quickly identify and address discrepancies in the project timeline.

Hightlighting out-of-range summary task