getConstraintLimitations

returns the earliest and latest dates allowed by the constraint applied to a task

void getConstraintLimitations(object task);

Parameters

taskobjecta task object

Example

gantt.addTaskLayer(function draw_deadline(task) {
    var constraintType = gantt.getConstraintType(task);
    var types = gantt.config.constraint_types;
    if (constraintType != types.ASAP && 
            constraintType != types.ALAP && task.constraint_date) {
 
        var dates = gantt.getConstraintLimitations(task);
 
        var els = document.createElement("div");
 
        if (dates.earliestStart) {
            els.appendChild(renderDiv(
                task, 
                dates.earliestStart, 
                'constraint-marker earliest-start'
            ));
        }
 
        if (dates.latestEnd) {
            els.appendChild(renderDiv(
                task, 
                dates.latestEnd, 
                'constraint-marker latest-end'
            ));
        }
 
        if (els.children.length)
            return els;
    }
    return false;
});
 
function renderDiv(task, date, className) {
    var el = document.createElement('div');
    el.className = className;
    var sizes = gantt.getTaskPosition(task, date);
    el.style.left = sizes.left + 'px';
    el.style.top = sizes.top + 'px';
    return el;
}

Related samples

Details

The return value has the following structure:

{
    earliestStart: Date || null,
    earliestEnd: Date || null,
    latestStart: Date || null,
    latestEnd: Date || null
}
See also