constraint_types

info

This functionality is available in the PRO edition only.

Description

Contains all available constraint types

constraint_types: { ASAP?: string; ALAP?: string; SNET?: string; SNLT?: string; FNET?: string; FNLT?: string; MSO?: string; MFO?: string; }

Details

The object definition:

  • ASAP - (string) - As Soon As Possible
  • ALAP - (string) - As Late As Possible
  • SNET - (string) - Start No Earlier Than
  • SNLT - (string) - Start No Later Than
  • FNET - (string) - Finish No Earlier Than
  • FNLT - (string) - Finish No Later Than
  • MSO - (string) - Must Start On
  • MFO - (string) - Must Finish On
gantt.config.constraint_types = {
// As Soon As Possible
ASAP: "asap",
// As Late As Possible
ALAP: "alap",
// Start No Earlier Than
SNET: "snet",
// Start No Later Than
SNLT: "snlt",
// Finish No Earlier Than
FNET: "fnet",
// Finish No Later Than
FNLT: "fnlt",
// Must Start On
MSO: "mso",
// Must Finish On
MFO: "mfo"
};

It is added in order to avoid hardcoding constraint values in code:

gantt.addTaskLayer(function draw_deadline(task) {
var constraintType = gantt.getConstraintType(task);
var types = gantt.config.constraint_types;
if (constraintType != types.ASAP &&
constraintType != types.ALAP && task.constraint_date) {
// display something
}
return false;
});