Description

Stores the types of links dependencies

links: { finish_to_start?: string | number; start_to_start?: string | number; finish_to_finish?: string | number; start_to_finish?: string | number; }

Example

var type1 = gantt.config.links.finish_to_start;

Default value:{ "finish_to_start":"0", "start_to_start":"1", "finish_to_finish":"2", "start_to_finish":"3" }

Details

  • finish_to_start - (string | number) - the target task can't start before the source task ends (but it may start later).
  • start_to_start - (string | number) - the target task can't start until the source task starts (but it may start later).
  • finish_to_finish - (string | number) - the target task can't end before the source task ends (but it may end later).
  • start_to_finish - (string | number) - the target task can't end before the source task starts (but it may end later).