Working time and calendars#
This guide shows how to tell Planning Engine when work can happen: working hours, weekdays, holidays and short days. It also covers how tasks and resources pick a calendar, and how to turn calendars off.
How calendars work#
A task's duration is working time. A 16-hour task doesn't end 16 hours after it starts. It ends once it has used 16 hours of its calendar's working time, so nights, weekends and holidays stretch it. Lags work the same way. levelingDelay and pauses are the exception: they're elapsed wall-clock time.
A calendar is a CalendarData: an id plus an optional Worktime with three parts:
hours: the working ranges of a day, asTimeRangevalues in minutes since midnight. Default: 08:00-12:00 and 13:00-17:00.days: aboolean[]of exactly seven flags, index 0 is Sunday. Default: Monday to Friday.dates: exceptions in aSortedDict<Moment, DayRule>, keyed by the date's midnightMoment. ADayRulemakes a dateDayRule.Off,DayRule.On(working with the calendar'shours) or working with its ownDayRule.Hoursranges.
Every project has a calendar named "global". If you don't define one, the engine uses the built-in Monday-Friday, 08:00-12:00 and 13:00-17:00. A calendar in ProjectData.calendars with the id "global" replaces it.
Which calendar a piece of work uses depends on SchedulingConfig.calendarMode (CalendarMode):
| Mode | A task works on |
|---|---|
RESOURCE (default) |
each assignment's calendar: the resource's calendar, intersected with the task's own calendar when both are set |
TASK |
the task's calendarId, else "global"; resource calendars are ignored |
TASK_INHERITED |
the task's calendarId, else the nearest ancestor's, else "global" |
RESOURCE follows MS Project. TASK and TASK_INHERITED use task calendars only.
SchedulingConfig.useCalendars overrides all of this. It's true by default. Set it to false and every calendar becomes flat 24/7 time.
The engine validates calendars when you pass the data to Project#solve(data, โฆ) or Engine.schedule. These cases throw an unchecked InputException with the field path in path:
- a duplicate calendar id
- a calendar with no working time
- an hour range outside 00:00-24:00
dayswith a length other than 7- a task or resource
calendarIdthat names no calendar (for resources, only inRESOURCEmode) - in
RESOURCEmode, a task calendar and a resource calendar that share no weekly working time (reported atassignments[i])
Calendars are part of the snapshot only. SchedulingChanges can't add or edit a calendar. To change one, send the full data again with solve(data, โฆ). Edits can still point tasks and resources at existing calendars through calendarId.
Defining calendars#
Replace "global" to change the working week for the whole project. The calendar below works Monday to Friday, 09:00-17:00. Thursday the 13th is a short day and Friday the 14th is a holiday:
;
;
Output:
build: 2026-08-10 09:00 -> 2026-08-17 17:00
The 36 hours are Monday to Wednesday (24 h), the short Thursday (4 h) and the next Monday (8 h). The holiday and the weekend hold no work.
A Worktime field you leave as null keeps its default. new Worktime().withDays(...) changes the weekdays and keeps the 08:00-12:00, 13:00-17:00 hours. dates starts as an empty map, so you can also fill it in place with worktime.dates.put(...).
Date exception keys#
Worktime.dates is keyed by a full Moment, but only the date part counts. Use the date's midnight as the key, as the example does with at(13, 0).
Two keys on the same day collide. Put a rule at 00:00 and another at 12:00 on the same date, and the later one replaces the earlier rule without an error. Build every key at midnight and this can't happen.
Task calendars#
Set TaskData.calendarId to run one task on a different calendar. Here the migrate task runs on a night shift, while review stays on the default "global" calendar:
;
;
Output:
review: 2026-08-10 08:00 -> 2026-08-11 17:00
migrate: 2026-08-10 22:00 -> 2026-08-12 06:00
The night shift's days are the default Monday to Friday. Monday's shift runs until Tuesday 06:00, because a range that crosses midnight belongs to the day it starts on.
A task's own calendar (else "global") also matters in RESOURCE mode. Milestones, lag without a link calendar and slack always use it.
Inheriting a calendar from a summary#
In TASK and RESOURCE modes a child doesn't look at its parent's calendar. Switch to CalendarMode.TASK_INHERITED to make a task without a calendarId use the nearest ancestor's:
;
;
Output:
pour: 2026-08-14 08:00 -> 2026-08-15 17:00
phase: 2026-08-14 08:00 -> 2026-08-15 17:00
pour works Friday and Saturday on the summary's six-day week. In the default mode it would wait for Monday.
Resource calendars#
In the default RESOURCE mode each assignment works on its resource's calendar, and the task's dates follow its assignments. Give a resource a calendar through ResourceData.calendarId. The example runs the same project in RESOURCE and TASK mode:
;
;
Output:
RESOURCE prepare: 2026-08-14 08:00 -> 2026-08-14 17:00
RESOURCE inspect: 2026-08-15 08:00 -> 2026-08-18 17:00
TASK prepare: 2026-08-14 08:00 -> 2026-08-14 17:00
TASK inspect: 2026-08-17 08:00 -> 2026-08-18 17:00
In RESOURCE mode Dana works Saturday, so inspect starts right after prepare and runs Saturday and Tuesday. In TASK mode her calendar is ignored and inspect waits for Monday on "global".
The rules for picking an assignment's calendar:
- The resource has a calendar and the task doesn't: the resource's calendar.
- Both have one: their intersection. Give a task a
morningscalendar and assign it to Dana, and the work runs Tuesday to Friday mornings only. - The resource has none: the task's calendar.
- Summaries and milestones always use the task's calendar.
A task with several assignments on different calendars spans the envelope of its assignments. Each assignment starts at the first working time of its own calendar and runs the full duration there. The task ends when the last one ends. The reported duration stays the working time of each assignment, not the length of the envelope. Results don't include per-assignment dates.
Resource calendars also shape resource load: each assignment books work only on its own calendar. See Resource load.
Flat time#
Set config.useCalendars to false to schedule without working hours. Every calendar becomes 24/7, so a day of duration is 24 hours:
;
;
Output:
burn-in: 2026-08-14 08:00 -> 2026-08-16 08:00
With calendars on, the same task skips the weekend and ends on Tuesday at 08:00. The engine still validates calendar ids, but they all resolve to the same flat time, so you can toggle useCalendars without touching the rest of the data. In flat mode resource and assignment edits never move dates.
Explicit starts on non-working time#
When an edit sets a start that falls on non-working time, the engine doesn't always snap it. A task with no predecessor keeps the exact start you gave it. Its end is computed forward on the working calendar, so the duration is still right. A task with a predecessor gets its start from the link instead.
;
;
Output:
deploy: 2026-08-15 10:00 -> 2026-08-17 12:00
The start stays on Saturday 10:00. The four hours of work run Monday 08:00-12:00. This applies to Project#apply and Project#preview, the calls behind drags in an editor.
This is by design: the UI layer owns snapping. If your editor should only allow working-time starts, snap the date before you send the TaskUpdate.