Conflict#
A scheduling conflict found while placing tasks. Instances come from ScheduleResult.conflicts, which lists every conflict of the run. A conflict is data in the result, not an exception. The run still succeeds and returns dates.
Declaration#
;
The library creates only these two nested subclasses. Read them with instanceof patterns or switch pattern matching. The hierarchy isn't sealed, so a switch over a Conflict needs a default arm.
Code refers to the variant as Conflict.ConstraintViolation. The package also has a top-level enum org.dhtmlx.plen.ConstraintViolation, and with import org.dhtmlx.plen.*; the bare name ConstraintViolation refers to that enum.
Variants#
| Variant | When it occurs |
|---|---|
Conflict.ConstraintViolation |
A task's constraint placed it at a date its driving dependency link doesn't allow. The constraint wins, and the task keeps the constraint's date. Reported only when SchedulingConfig.applyConstraints is true. |
Conflict.CalendarNonWorking |
A summary moved as one block, and a descendant task landed on non-working time of its calendar. Reported only when SchedulingConfig.strictCalendar is true. |
ConstraintViolation#
public
| Field | Type | Description |
|---|---|---|
task |
Id |
The task or summary whose constraint won. |
constraint |
ConstraintType |
The constraint that placed the task: the task's own, or one inherited from a summary. |
violation |
Violation |
Which bound the link contradicts. |
required |
Moment |
The date the constraint gave the task. The task has this date in the result. |
actual |
Moment |
The date the driving link would have given the task. |
CalendarNonWorking#
public
| Field | Type | Description |
|---|---|---|
task |
Id |
The descendant task that landed on non-working time. |
proposed |
Moment |
The task's new start, or its new end when the project is scheduled from the end. The date is on non-working time. |
snapped |
Moment |
The date the task keeps. Currently it's always equal to proposed: the task isn't moved to working time. |
Methods#
copy#
public Conflict
Returns a shallow copy. Each subclass overrides it with its own return type, such as Conflict.ConstraintViolation copy(). All fields are immutable values, so the copy is independent of the original.
Returns: a new instance of the same variant.
equals, hashCode, toString#
public boolean
public int
public String
Inherited from ValueRecord. Two conflicts are equal when they're the same variant and all their fields are equal. toString() prints the variant and its fields, e.g. ConstraintViolation{task=demo, constraint=SNLT, violation=LATEST_START, required=2026-03-03 00:00, actual=2026-03-05 00:00}.
Violation#
Which bound of a constraint the driving link contradicts, in Conflict.ConstraintViolation.violation. EARLIEST_START and LATEST_START compare start dates. EARLIEST_END and LATEST_END compare end dates.
;
| Value | Description |
|---|---|
EARLIEST_START |
The link wants an earlier start than the constraint allows. |
LATEST_START |
The link wants a later start than the constraint allows. |
EARLIEST_END |
The link wants an earlier end than the constraint allows. |
LATEST_END |
The link wants a later end than the constraint allows. |
Example#
demo must start no later than Tuesday, but its predecessor build ends on Wednesday. The constraint wins, and the result reports the conflict:
;
;
Output:
demo: SNLT LATEST_START, constraint gives 2026-03-03 00:00, link wants 2026-03-05 00:00
The default arm is there only because the compiler requires it. The library returns no other variant.