Pause#
A gap in a task's work. at is the elapsed time from the task start to the start of the gap, and length is how long the gap lasts. Pauses go in TaskData.pauses and in TaskUpdate.pauses. Project#level writes them when it splits a task. Create one with new Pause(at, length) or Pause.leveling(at, length).
Declaration#
;
Every field is public and mutable, and has a withX(value) setter that assigns it and returns this. equals, hashCode and toString come from ValueRecord and compare at, length and by.
Constructors#
Pause(double, double)#
public
Creates a pause with by = null.
| Name | Type | Description |
|---|---|---|
at |
double |
Elapsed time from the task start to the pause start. |
length |
double |
Elapsed length of the pause. |
Fields#
| Field | Type | Default | Description |
|---|---|---|---|
at |
double |
constructor argument | Elapsed time from the task start to the pause start. Finite and >= 0. |
length |
double |
constructor argument | Elapsed length of the pause. Finite and > 0. |
by |
PauseSource |
null |
Who wrote the pause. The leveler always sets PauseSource.LEVELING. |
at, length#
public double at;
public double length;
public Pause
public Pause
Both values are elapsed (wall-clock) time in the task's durationUnit: a minute, an hour of 60 minutes, or a day of 24 hours. Fractions are allowed. When the task is scheduled, the pause occupies the whole minutes [round(at), round(at + length)). The two ends are rounded, not at and length on their own, so adjacent pauses never overlap after rounding. A pause that rounds to zero length is ignored.
A pause counts only while the task has work left after it. For how pauses shape a task's dates, see Leveling resources.
by#
public PauseSource by;
public Pause
Optional on input. Every pause in a project counts as leveling-owned, whatever by holds. See LevelingOptions for how the leveler clears and extends pauses.
Static methods#
leveling#
public static Pause
Returns a pause with by = PauseSource.LEVELING, the same value the leveler writes.
Methods#
deepClone#
public Pause
Returns a new pause with the same at, length and by.
copy#
public Pause
Returns a shallow copy. A pause holds only a double pair and an enum, so the result equals deepClone().
PauseSource#
Who created a pause.
;
| Value | Description |
|---|---|
LEVELING |
Created by resource leveling. The only value. |
Errors#
A task's pause list is validated when the snapshot is passed to Engine.schedule or Project#solve(data, …). The call throws InputException with kind = InputErrorKind.VALIDATION and path = "tasks[i].pauses[j]" when pause j:
- has an
atthat's negative,NaNor infinite - has a
lengththat's<= 0,NaNor infinite - starts before the previous pause ends, so the list isn't sorted by
ator two pauses overlap
at = 0 and adjacent pauses (one ends exactly where the next starts) are valid. The overlap check forgives floating-point error up to 1e-9 × max(1, end), where end is the previous pause's at + length. Minute-exact fractions such as 1.0/60 + 31.0/60 against 32.0/60 pass.
The list is validated on every task kind, but pauses have no effect on summaries, milestones and unscheduled tasks.
Validation.REPAIR clears an invalid list instead of throwing and records a Note.Repaired at tasks[i].pauses. Pause lists changed after the first solve go through TaskUpdate, which runs the same checks.
Example#
A three-day task that stops for a day, one day after it starts:
;
;
Related#