timeline_cell_class

Description

Specifies the CSS class that will be applied to the cells of the timeline area

timeline_cell_class: (item: any, date: Date) => string | void;

Parameters

  • item - (required) Task | object - either the task's or resource's object assigned to the row
  • date - (required) Date - the date of a cell

Returns

  • text - (string | void) - a CSS class for the item in question

Example

<style>
.weekend{ background: #f4f7f4 !important;}
</style>

gantt.templates.timeline_cell_class = function(task,date){
if(date.getDay()==0||date.getDay()==6){
return "weekend";
}
};

Details

Note that while using work time calculations, you can use isWorkTime instead of hardcoded values:

gantt.config.work_time = true;

gantt.templates.timeline_cell_class = function(task,date){
if(!gantt.isWorkTime({task:task, date:date}))
return "weekend";
};