timeline_cell_class
Description
Specifies the CSS class that will be applied to the cells of the timeline area
timeline_cell_class: (item: any, date: Date) => string | void;
Parameters
item- (required) Task | object - either the task's or resource's object assigned to the rowdate- (required) Date - the date of a cell
Returns
text- (string | void) - a CSS class for the item in question
Example
<style>
.weekend{ background: #f4f7f4 !important;}
</style>
gantt.templates.timeline_cell_class = function(task,date){
if(date.getDay()==0||date.getDay()==6){
return "weekend";
}
};
Related samples
Details
Note that while using work time calculations, you can use isWorkTime instead of hardcoded values:
gantt.config.work_time = true;
gantt.templates.timeline_cell_class = function(task,date){
if(!gantt.isWorkTime({task:task, date:date}))
return "weekend";
};