Resource Leveling and Paused Tasks

Resource leveling can delay or pause work to avoid overbooking a resource. To calculate a leveled schedule in Gantt, enable the PRO auto_scheduling plugin and select a provider that supports resource leveling. You can also load and display a leveled schedule calculated elsewhere.

Store a leveled plan​

A task stores the actual start and end dates of the leveled plan. It can also contain these fields.

FieldMeaning
leveling_delayA finite, nonnegative number. It records how far a task shifts from the date implied by its dependency links. Use 0 to clear the delay.
pausesAn array of records in the form { at, length, by? }. Each record starts at an elapsed offset at from the task's start and lasts for length. Specify a nonnegative at and a positive length. Keep entries ordered and nonoverlapping. Adjacent pauses are allowed. A provider can mark its entries with by: "leveling". Use [] to clear pauses.

Both fields use elapsed time in the chart's duration_unit. A day is 24 elapsed hours, including non-working time. For example, { at: 2, length: 1 } on a chart configured in days means a one-day pause starting two elapsed days after the task starts.

When loading data, Gantt accepts a numeric string for the delay and a JSON-encoded array for pauses. Use numbers and arrays when updating tasks through the API. To update existing tasks from an external leveling result, supply the actual dates as Date objects and call updateTask for each task.

gantt.batchUpdate(() => {
for (const result of leveledTasks) {
const task = gantt.getTask(result.id);
task.start_date = result.start_date;
task.end_date = result.end_date;
task.leveling_delay = result.leveling_delay;
task.pauses = result.pauses;
gantt.updateTask(task.id);
}
});

The built-in scheduler uses the delay to shift a task's start later in forward scheduling, or its end earlier in backward scheduling. Constraints may limit the shift. Clear existing adjustments or level again if you change scheduling direction. Manually changing the leading date clears the delay through the auto-scheduling edit flow. Changing only the trailing edge keeps the delay. Moving the task moves its pauses with it.

Show the delay in the timeline​

информация

This functionality is available in the PRO edition only.

Enable the leveling_delays config to show the delay in the timeline. Gantt draws a hatched area next to each task that has a leveling_delay. In forward scheduling, the area lies before the bar. With backward scheduling, it lies after the bar. Set the config before gantt.init().

gantt.config.leveling_delays = true;
gantt.templates.leveling_delay_text = function(task, delay, unit) {
return "delay " + delay + " d";
};
gantt.init("gantt_here");

The leveling_delay_text template sets the label and the tooltip of the area. The default text is the delay with a short unit name, for example "+2d".

The area has the gantt_leveling_delay CSS class, and also gantt_leveling_delay_forward or gantt_leveling_delay_backward. To change its color, set the --dhx-gantt-leveling-delay-color variable. By default, it is the task bar color.

:root {
--dhx-gantt-leveling-delay-color: #7a7a7a;
}

Edit the delay in the task form​

Add a stepper section to the lightbox to edit leveling_delay in the task form. The samples/11_resources/16_leveling_delay.html sample uses this configuration:

gantt.config.lightbox.sections = [
{ name: "description", height: 70, map_to: "text", type: "textarea", focus: true },
{ name: "leveling_delay", label: "Leveling delay, days", type: "stepper",
map_to: "leveling_delay", min: 0, step: 1 },
{ name: "time", type: "duration", map_to: "auto" }
];

Saving the form with an empty field clears the delay. step: 1 snaps an edited value to whole units. A stored fractional delay stays unchanged when the user does not edit the field.

With auto scheduling enabled, a task-form save that changes only leveling_delay reschedules the task, and so does a change made inside gantt.ext.autoScheduling.asUserEdit(). Both follow the rules of an interactive edit under the existing constraints. A longer delay moves the task further from the date its dependency links imply. A shorter or cleared delay moves the task back only as far as an interactive edit allows. A task without predecessors keeps its start.

The task's stored constraint is kept, both in constraint mode and in preferred-date mode. A remedy chosen to resolve a constraint conflict can still change constraints. Cancelling the conflict restores the original delay, or removes leveling_delay if the task did not have it. With the Undo plugin, one undo restores the delay and the dates from before the save.

заметка

A plain gantt.updateTask() that changes leveling_delay does not reschedule the task. An inline editor mapped to leveling_delay does not reschedule it either. Call gantt.autoSchedule() afterwards, or make the change inside asUserEdit().

Schedule a task with pauses​

Pauses affect regular scheduled tasks when duration_unit is "minute", "hour", or "day" and duration_step is 1. Gantt fits work into the working time outside the pauses. A pause that falls entirely in non-working time or after the task's work finishes adds no time to the task.

With a start date and a duration, Gantt derives the end date including the interruption. With both dates, Gantt uses them to find the work duration. Supply the start date for paused tasks because calculating backward from an end date and duration does not account for pauses.

gantt.config.work_time = true;
gantt.config.duration_unit = "day";
gantt.config.duration_step = 1;
gantt.init("gantt_here");

gantt.parse({
tasks: [{
id: 1,
text: "Review",
start_date: new Date(2027, 3, 5),
duration: 5,
pauses: [{ at: 2, length: 1 }]
}]
});

const task = gantt.getTask(1);
const work = gantt.calculateDuration(task);
const span = gantt.getTaskCalendar(task).calculateDuration({
start_date: task.start_date,
end_date: task.end_date
});

With the default work calendar, the task pauses on Wednesday and has five days of work across six working days. Pass the task to calculateDuration or calculateEndDate for calculations that account for its pauses. Call the calendar directly to measure the working span, including scheduled work time during a pause.

A paused task stays in one task record. Gantt draws gaps between its work segments and places the label on the widest segment. To model individually dated child tasks on the same row, use split tasks. The standard bar for a paused task has no progress indicator. To change a pause entry, update the task data.

Assignments and resource load​

An assignment's delay and fixed duration count the work of the task from its start. Gantt skips pauses while counting, so assignments can start or end later. A resource histogram cell that falls wholly inside a pause does not count the task. A cell with scheduled work outside the pause can still count the assignment.

Effort-driven calculations do not support paused tasks. The PDF and PNG export service can render a single bar instead of the paused segments. MS Project import and export do not preserve pause records.