Effort-Driven Tasks
Use effort-driven scheduling to control how Gantt adjusts a task's work, working duration and resource allocation when you edit one of those values. The workflow below uses Gantt PRO resource assignments.
Enable effort calculations
Set effort.enabled before initializing Gantt and supply task assignment values. Each assignment's value is the allocation per full workday in the configured work unit. With the default values, 8 is a full allocation and 4 is half.
Gantt calculates work as the task's working span multiplied by the total assignment value divided by hours_per_day. The working span and work are measured in effort.work_unit. The task's duration keeps its own duration unit.
gantt.config.work_time = true;
gantt.config.effort = {
enabled: true,
mode: "fixed_work",
effort_driven: false,
work_unit: "hour",
hours_per_day: 8
};
gantt.init("gantt_here");
gantt.parse({
resources: [{ id: 2, text: "Maya" }, { id: 3, text: "Noah" }],
tasks: [{
id: 1,
text: "Prepare design",
start_date: new Date(2027, 3, 5),
duration: 5,
owner_id: [{ resource_id: 2, value: 8 }]
}]
});
const task = gantt.getTask(1);
task.owner_id = [
{ resource_id: 2, value: 8 },
{ resource_id: 3, value: 8 }
];
gantt.updateTask(1);
const work = gantt.getTaskWork(1);
With the default work calendar, adding a second full allocation changes the span from 40 to 20 working hours, leaving 40 hours of work. If you set a different resource_property, use that property instead of owner_id.
Choose a scheduling mode
Use task.scheduling_mode or the configured default mode. In Fixed duration, an assignment allocation change recalculates work. In Fixed units or Fixed work, it recalculates duration. When the number of assignments changes, the task's effort_driven flag also matters.
| Edit | Fixed duration | Fixed units | Fixed work |
|---|---|---|---|
| Duration changes | Recalculate work | Recalculate work | Redistribute allocation |
| Work changes | Redistribute allocation | Recalculate duration | Recalculate duration |
| Existing allocation changes | Recalculate work | Recalculate duration | Recalculate duration |
Add or remove an assignment, effort_driven: false | Recalculate work | Recalculate work | Recalculate duration |
Add or remove an assignment, effort_driven: true | Redistribute allocation | Recalculate duration | Recalculate duration |
Allocation is redistributed proportionally, or evenly if all current allocation values are zero. Gantt keeps the start date when deriving a new duration. Rounding and the minimum duration can affect the resulting work. With zero total allocation, Gantt cannot derive a duration from work.
Gantt uses configured defaults for tasks that omit scheduling_mode or effort_driven. A leaf task's supplied work is preserved on load. If no work is supplied, Gantt derives it from the task's working span and assignments. Summary work is calculated from child work. Use getTaskWork to read it.
Effort calculations also apply to assignment edits submitted through the advanced task form or through task updates inside batchUpdate. They do not support paused tasks.
Editing effort fields
Add a Work column using task_work. Use a number editor for ordinary tasks and display the rolled-up work on summary rows. To edit the task's mode, map a select editor to scheduling_mode and provide the mode values as options. In the classic lightbox, use a field mapped to work, a select mapped to scheduling_mode, and a checkbox mapped to effort_driven.
const labels = gantt.locale.labels;
const modes = [
{ key: "fixed_duration", label: labels.fixed_duration },
{ key: "fixed_units", label: labels.fixed_units },
{ key: "fixed_work", label: labels.fixed_work }
];
gantt.config.columns = [
{ name: "text", tree: true, width: "*" },
{
name: "work",
label: labels.column_work,
template: task => gantt.templates.task_work(task),
editor: { type: "number", map_to: "work" }
},
{
name: "scheduling_mode",
label: labels.section_scheduling_mode,
template: task => task.scheduling_mode ? labels[task.scheduling_mode] : "",
editor: { type: "select", map_to: "scheduling_mode", options: modes }
}
];
gantt.ext.inlineEditors.attachEvent("onBeforeEditStart", ({ id, columnName }) => {
return columnName !== "work" || !gantt.isSummaryTask(gantt.getTask(id));
});
For custom locales, set column_work, section_work, section_scheduling_mode, fixed_duration, fixed_units and fixed_work. Provide the caption for a custom effort-driven checkbox in the field configuration or your app's locale.
Framework integrations
- React's useEffortDriven hook reads and updates effort fields through the wrapper ref.
- Vue's useEffortDriven composable exposes the same helpers as a computed value.
- Angular uses the Gantt instance received through the
readyevent.