Inactive Tasks and Links
Set active: false on a task or link to keep it in the project while excluding it from
auto scheduling. Gantt applies an inactive style to the task row,
bar or dependency line. Set active: true or omit the field to allow the item to participate.
Deactivate a task or link
Include active: false when you load or add the item. For an item already loaded, change its
property and call the corresponding update method:
const task = gantt.getTask(taskId);
task.active = false;
gantt.updateTask(taskId);
const link = gantt.getLink(linkId);
link.active = false;
gantt.updateLink(linkId);
Use the update methods to synchronize the change with scheduling and rendering. If you save the
project to a server, store active with the task or link data.
To change a dependency's activity from the timeline, use Activate link or Deactivate link in the built-in context menu.
How Gantt determines activity
- A task is inactive if its own
activefield or that of any ancestor isfalse. Deactivating a summary task leaves its descendants' stored flags intact. - A link is inactive if its own
activefield isfalseor either endpoint is inactive. In a chain A → B → C, deactivating B removes both dependencies from scheduling. Gantt does not create a dependency from A to C.
Use isTaskActive and isLinkActive to check the effective state:
const taskParticipates = gantt.isTaskActive(taskId);
const linkParticipates = gantt.isLinkActive(linkId);
Effects on the project
- Inactive tasks keep their dates. The scheduler skips them, and they do not drive their successors or appear on the critical path.
- An active summary skips inactive children when deriving its dates and calculating subtask duration. It also skips them in rollup bars and split-task displays. An inactive summary still derives its span from its children.
- In the built-in resource panel, inactive tasks do not contribute to resource load.
Customize the inactive style
| CSS variable | Affects |
|---|---|
--dhx-gantt-inactive-background | Task bar background |
--dhx-gantt-inactive-color | Task bar text |
--dhx-gantt-inactive-border | Task bar border, dashed by default |
--dhx-gantt-inactive-opacity | Grid row and link opacity |
The matching CSS classes are gantt_task_inactive on the task bar, gantt_row_inactive on
the grid row, gantt_task_row_inactive on the timeline row, and gantt_link_inactive on the
link.
The samples/02_extensions/30_inactive_tasks.html example shows an Active checkbox in the
grid, a link you can deactivate, and a complete inactive project branch.