检查给定任务是否为关键任务
| task | Task | 要检查的任务对象 |
| boolean | 如果任务是关键任务则返回 'true',否则返回 'false' |
Available only in PRO Edition
const tasks = {
data:[
{id:1, text:"Project #1", start_date:"01-04-2023", duration:18, type:"project"},
{id:2, text:"Task #1", start_date:"02-04-2023", duration:8, parent:1},
{id:3, text:"Task #2", start_date:"13-04-2023", duration:8, parent:1}
],
links:[
{id:1, source:1, target:2, type:"1"},
{id:2, source:2, target:3, type:"0"}
]
};
gantt.config.highlight_critical_path = true; gantt.init("gantt_here");
gantt.parse(tasks);
gantt.isCriticalTask(gantt.getTask(2));// ->'false' gantt.isCriticalTask(gantt.getTask(3));// ->'true'
该功能仅在 PRO 版本中提供。
此方法是 critical_path 扩展的一部分,因此请确保启用 critical_path 插件。更多信息,请参阅 关键路径 文章。