# Metrics

The scores of one plan state against the solved baseline: project and focus-task finish, resource overload, conflict and cycle counts, and one `cost` number for ranking. `Metrics` is a response payload only. [`JsonProject.evaluate`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-evaluate.md>) returns it for the baseline and for the scheduled stage of each candidate, and [`JsonProject.suggestAssignments`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-suggest-assignments.md>) returns it for the proposed state. The leveled stage comes as [`LeveledMetrics`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#leveledmetrics>): the same fields plus a leveling summary.

Every measurement is an absolute value plus a `delta` against the baseline. In the baseline's own metrics, every delta is `0`.

## Fields

| Field | Type | Description |
|---|---|---|
| `finish` | [`object`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#finish-fields>) | Finish of the project and of each focus task |
| `overload` | [`object`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#overload-fields>) | Resource overload: total, per resource and per focus task |
| `conflicts` | [`Amount`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#amount>) | Number of conflicts in the stage's schedule result |
| `cycles` | [`Amount`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#amount>) | Number of dependency cycles in the stage's schedule result. Above `0` when the stage is cyclic |
| `cost` | number | Ranking score of the stage. Lower is better. See [Cost](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#cost>) |

Every field is always present.

### Finish fields

| Field | Type | Description |
|---|---|---|
| `project` | [`Shift`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#shift>) \| `null` | Latest end over the scheduled tasks. `null` when the stage has no tasks. The `delta` is measured on the global calendar, and it's `0` when the baseline has no tasks |
| `tasks` | [`object`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#focus-task-finish>)`[]` | One entry per focus task, in `focus` order. Empty without focus tasks |

### Focus task finish

| Field | Type | Description |
|---|---|---|
| `id` | [`Id`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/common.md#id>) | The focus task |
| `finish` | [`Shift`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#shift>) \| `null` | The task's end. The `delta` is measured on the task's calendar. `null` when the task isn't in the stage, for example after the candidate removed it |

### Overload fields

Overload is the sum over time buckets of how far a resource's load goes over its capacity: Σ `max(0, load − capacity)`. The unit is capacity × buckets, so on a `"day"` basis, `2` means two resource-days over. The baseline and every stage of every candidate use one bucket size: `level.basis` when the options give it, otherwise the basis derived from `config.duration_unit`.

| Field | Type | Description |
|---|---|---|
| `total` | [`Amount`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#amount>) | Overload summed over all resources |
| `resources` | [`ResourceOverload`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#resourceoverload>)`[]` | One entry per resource that's non-zero in the stage or in the baseline. Resources in stage order come first, then resources that are non-zero only in the baseline |
| `focus` | [`object`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#focus-task-overload>)`[]` | One entry per focus task, in `focus` order. Empty without focus tasks |

### ResourceOverload

| Field | Type | Description |
|---|---|---|
| `resource` | [`Id`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/common.md#id>) | The resource |
| `overload` | [`Amount`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#amount>) | The resource's overload. `value` can be `0` when the resource is overloaded only in the baseline |

### Focus task overload

| Field | Type | Description |
|---|---|---|
| `task` | [`Id`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/common.md#id>) | The focus task |
| `resources` | [`ResourceOverload`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#resourceoverload>)`[]` \| `null` | Overload per resource, summed over the buckets that intersect the task's `[start, end)` in this stage. Lists every resource that's non-zero there in the stage or in the baseline, in the same order as `overload.resources`. `null` when the task isn't in the stage. A zero-length milestone covers no bucket |

### Shift

A date and its distance from the baseline date.

| Field | Type | Description |
|---|---|---|
| `date` | [`DateValue`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/common.md#datevalue>) | The date in this stage, as `YYYY-MM-DD HH:mm` |
| `delta` | number | Working time from the baseline date to `date`, in `config.duration_unit`. Positive when later |

### Amount

A count or a sum and its difference from the baseline.

| Field | Type | Description |
|---|---|---|
| `value` | number | The value in this stage |
| `delta` | number | `value` minus the baseline's value |

### Cost

`cost` is one fixed formula:

```text
cost = max(0, finish.project.delta)
     + overload.total.value
     + 1000 × (conflicts.value + cycles.value)
```

An earlier finish earns no bonus. The `1000` penalty puts any stage with conflicts or cycles behind every stage without them. To rank by other rules, read the raw fields instead. How the stages are scored and compared is covered in [Evaluating Alternatives](<https://docs.dhtmlx.com/planning-engine/wasm/resources-and-assignment/evaluating-alternatives.md#metrics-and-cost>).

## LeveledMetrics

The metrics of the leveled stage. All `Metrics` fields sit flat in the same object, next to a summary of the leveling run. Present only when the call's options set `level`.

| Field | Type | Description |
|---|---|---|
| `finish`, `overload`, `conflicts`, `cycles`, `cost` | | As in [`Metrics`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/metrics.md#fields>), measured after leveling |
| `converged` | boolean | Whether the final scheduling pass after leveling reached a fixed point within `max_iterations`. Same as `converged` in the [`level`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-level.md>) result |
| `rounds` | number | Leveling rounds that proposed a correction. As `rounds` in the `level` result |
| `windows` | number | Overallocation windows left after leveling, whatever their reason |

At the leveled stage, focus overload shows what leveling couldn't resolve around the task.

## Used by

- [`JsonProject.evaluate`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-evaluate.md>): [`EvaluateResult`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-evaluate.md#evaluateresult>)`.baseline` (`Metrics`), and `scheduled` (`Metrics`) and `leveled` (`LeveledMetrics`) of each [`CandidateResult`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-evaluate.md#candidateresult>)
- [`JsonProject.suggestAssignments`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-suggest-assignments.md>): `scheduled` (`Metrics`) and `leveled` (`LeveledMetrics`) of [`SuggestProposal`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-suggest-assignments.md#suggestproposal>)

## Example

Two tasks of 2 days each, both on `dev1` at full capacity, with task `B` in `focus`. The baseline `Metrics`: `dev1` is 2 resource-days over, and nothing is late yet.

```json
{
  "conflicts": { "delta": 0, "value": 0 },
  "cost": 2,
  "cycles": { "delta": 0, "value": 0 },
  "finish": {
    "project": { "date": "2026-08-12 08:00", "delta": 0 },
    "tasks": [{ "finish": { "date": "2026-08-12 08:00", "delta": 0 }, "id": "B" }]
  },
  "overload": {
    "focus": [
      { "resources": [{ "overload": { "delta": 0, "value": 2 }, "resource": "dev1" }], "task": "B" }
    ],
    "resources": [{ "overload": { "delta": 0, "value": 2 }, "resource": "dev1" }],
    "total": { "delta": 0, "value": 2 }
  }
}
```

The `LeveledMetrics` of the unchanged plan after leveling: the overload is gone, and `B` and the project finish 2 days later.

```json
{
  "conflicts": { "delta": 0, "value": 0 },
  "converged": true,
  "cost": 2,
  "cycles": { "delta": 0, "value": 0 },
  "finish": {
    "project": { "date": "2026-08-14 08:00", "delta": 2 },
    "tasks": [{ "finish": { "date": "2026-08-14 08:00", "delta": 2 }, "id": "B" }]
  },
  "overload": {
    "focus": [
      { "resources": [{ "overload": { "delta": -2, "value": 0 }, "resource": "dev1" }], "task": "B" }
    ],
    "resources": [{ "overload": { "delta": -2, "value": 0 }, "resource": "dev1" }],
    "total": { "delta": -2, "value": 0 }
  },
  "rounds": 2,
  "windows": 0
}
```

## Related

- [`JsonProject.evaluate`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-evaluate.md>) - scores candidate change sets
- [`JsonProject.suggestAssignments`](<https://docs.dhtmlx.com/planning-engine/wasm/api/project-suggest-assignments.md>) - scores assignment proposals
- [`LevelingOptions`](<https://docs.dhtmlx.com/planning-engine/wasm/api/types/leveling-options.md>) - the `level` option that adds the leveled stage
- [Evaluating Alternatives](<https://docs.dhtmlx.com/planning-engine/wasm/resources-and-assignment/evaluating-alternatives.md>) - comparing candidates by cost
- [Suggesting assignments](<https://docs.dhtmlx.com/planning-engine/wasm/resources-and-assignment/suggesting-assignments.md>) - how proposals are scored