[Canonical page](<https://docs.dhtmlx.com/planning-engine/rust/scheduling/working-time-calendars/>)
[Full documentation index](<https://docs.dhtmlx.com/planning-engine/llms.txt>)


# Working time and calendars

This guide shows how to tell Planning Engine when work can happen: working hours, weekdays, holidays and short days. It also covers how tasks and resources pick a calendar and how to turn calendars off.

## How calendars work

A task's `duration` is **working time**. A 16-hour task doesn't end 16 hours after it starts. It ends once it has used 16 hours of its calendar's working time, so nights, weekends and holidays stretch it. Lags work the same way. `leveling_delay` and `pauses` are the exception: they're elapsed wall-clock time.

A calendar is a [`CalendarData`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/data/calendar-data.md>): an `id` plus an optional [`Worktime`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/data/worktime.md>) with three parts:

- `hours`: the working ranges of a day, as [`TimeRange`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/data/time-range.md>) values in minutes since midnight. Default: 08:00-12:00 and 13:00-17:00.
- `days`: seven flags, **index 0 is Sunday**. Default: Monday to Friday.
- `dates`: exceptions keyed by `chrono::NaiveDate`. A [`DayRule`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/data/day-rule.md>) makes a date `Off`, `On` (working with the calendar's `hours`) or working with its own `Hours(...)`.

Every project has a calendar named `"global"`. If you don't define one, the engine uses the built-in Monday-Friday, 08:00-12:00 and 13:00-17:00. A calendar in `ProjectData.calendars` with the id `"global"` replaces it.

Which calendar a piece of work uses depends on `config.calendar_mode` ([`CalendarMode`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/data/calendar-mode.md>)):

| Mode | A task works on |
|---|---|
| `Resource` (default) | each assignment's calendar: the resource's calendar, intersected with the task's own calendar when both are set |
| `Task` | the task's `calendar_id`, else `"global"`; resource calendars are ignored |
| `TaskInherited` | the task's `calendar_id`, else the nearest ancestor's, else `"global"` |

`Resource` follows MS Project. `Task` and `TaskInherited` follow dhtmlxGantt, which only knows task calendars.

`config.use_calendars` sits above all of this. It's `true` by default. Set it to `false` and every calendar becomes flat 24/7 time.

The engine validates calendars when you pass the data to [`solve(Some(data))`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/project/project.md#solve>) or [`schedule`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/project/schedule.md>). These cases fail with [`Error::Input`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/errors/error.md>) at the field path:

- a duplicate calendar id
- a calendar with no working time
- an hour range outside 00:00-24:00
- a task or resource `calendar_id` that names no calendar (for resources, only in `Resource` mode)
- in `Resource` mode, a task calendar and a resource calendar that share no weekly working time (reported at `assignments[i]`)

Calendars are part of the snapshot only. [`SchedulingChanges`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/changes/scheduling-changes.md>) can't add or edit a calendar. To change one, send the full data again with `solve(Some(data))`. Edits can still point tasks and resources at existing calendars through `calendar_id`.

## Defining calendars

Replace `"global"` to change the working week for the whole project. The calendar below works Monday to Friday, 09:00-17:00. Thursday the 13th is a short day and Friday the 14th is a holiday:

```rust
use std::collections::BTreeMap;

use chrono::NaiveDate;
use plen_core::{
    schedule, CalendarData, DateTime, DayRule, ProjectData, SolveOptions, TaskData, TimeRange,
    TimeUnit, Worktime,
};

fn main() -> Result<(), Box<dyn std::error::Error>> {
    let date = |d: u32| NaiveDate::from_ymd_opt(2026, 8, d).ok_or("invalid date");

    let mut dates = BTreeMap::new();
    // Thursday: a short day, 09:00-13:00.
    dates.insert(date(13)?, DayRule::Hours(vec![TimeRange { start: 9 * 60, end: 13 * 60 }]));
    // Friday: a public holiday.
    dates.insert(date(14)?, DayRule::Off);

    let global = CalendarData {
        id: "global".into(),
        worktime: Some(Worktime {
            hours: Some(vec![TimeRange { start: 9 * 60, end: 17 * 60 }]),
            days: Some([false, true, true, true, true, true, false]), // Sun..Sat
            dates,
        }),
    };

    let mut task = TaskData::new("build");
    task.start_date = DateTime::from_ymd_hm(2026, 8, 10, 9, 0); // Monday
    task.duration = Some(36.0);

    let mut data = ProjectData {
        calendars: vec![global],
        tasks: vec![task],
        ..Default::default()
    };
    data.config.duration_unit = TimeUnit::Hour;

    let options = SolveOptions { include_unchanged: true, ..Default::default() };
    let result = schedule(data, &options)?;
    for update in &result.updates {
        if let (Some(start), Some(end)) = (update.start_date, update.end_date) {
            println!("{}: {start} -> {end}", update.id);
        }
    }
    Ok(())
}
```

Output:

```text
build: 2026-08-10 09:00 -> 2026-08-17 17:00
```

The 36 hours are Monday to Wednesday (24 h), the short Thursday (4 h) and the next Monday (8 h). The holiday and the weekend hold no work. The example needs `chrono` as a dependency for `NaiveDate` (`cargo add chrono`).

A field you leave as `None` keeps its default. `Worktime { days: Some(...), ..Default::default() }` changes the weekdays and keeps the 08:00-12:00, 13:00-17:00 hours.

## Task calendars

Set `TaskData.calendar_id` to run one task on a different calendar. Here the `migrate` task runs on a night shift, while `review` stays on the default `"global"` calendar:

```rust
use plen_core::{
    schedule, CalendarData, DateTime, ProjectData, SolveOptions, TaskData, TimeRange, TimeUnit,
    Worktime,
};

fn main() -> Result<(), Box<dyn std::error::Error>> {
    // 22:00-06:00: the range ends before it starts, so it crosses midnight
    // and belongs to the day it starts on.
    let night = CalendarData {
        id: "night".into(),
        worktime: Some(Worktime {
            hours: Some(vec![TimeRange { start: 22 * 60, end: 6 * 60 }]),
            ..Default::default()
        }),
    };

    let mut review = TaskData::new("review");
    review.start_date = DateTime::from_ymd_hm(2026, 8, 10, 8, 0);
    review.duration = Some(16.0);

    let mut migrate = TaskData::new("migrate");
    migrate.start_date = DateTime::from_ymd_hm(2026, 8, 10, 22, 0);
    migrate.duration = Some(16.0);
    migrate.calendar_id = Some("night".into());

    let mut data = ProjectData {
        calendars: vec![night],
        tasks: vec![review, migrate],
        ..Default::default()
    };
    data.config.duration_unit = TimeUnit::Hour;

    let options = SolveOptions { include_unchanged: true, ..Default::default() };
    let result = schedule(data, &options)?;
    for update in &result.updates {
        if let (Some(start), Some(end)) = (update.start_date, update.end_date) {
            println!("{}: {start} -> {end}", update.id);
        }
    }
    Ok(())
}
```

Output:

```text
review: 2026-08-10 08:00 -> 2026-08-11 17:00
migrate: 2026-08-10 22:00 -> 2026-08-12 06:00
```

The night shift's days are the default Monday to Friday. Monday's shift runs until Tuesday 06:00, because a range that crosses midnight belongs to the day it starts on. Ranges that cross midnight are a Planning Engine extension to the dhtmlxGantt calendar format.

A task's own calendar (else `"global"`) also matters in `Resource` mode. Milestones, lag without a link calendar and slack always use it.

### Inheriting a calendar from a summary

In `Task` and `Resource` modes a child doesn't look at its parent's calendar. Switch to [`CalendarMode::TaskInherited`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/data/calendar-mode.md>) to make a task without a `calendar_id` use the nearest ancestor's:

```rust
use plen_core::{
    schedule, CalendarData, CalendarMode, DateTime, ProjectData, SolveOptions, TaskData, TaskType,
    TimeUnit, Worktime,
};

fn main() -> Result<(), Box<dyn std::error::Error>> {
    let six_day_week = CalendarData {
        id: "six-day".into(),
        worktime: Some(Worktime {
            days: Some([false, true, true, true, true, true, true]),
            ..Default::default()
        }),
    };

    let mut phase = TaskData::new("phase");
    phase.task_type = TaskType::Summary;
    phase.calendar_id = Some("six-day".into());

    let mut pour = TaskData::new("pour");
    pour.parent = Some("phase".into());
    pour.start_date = DateTime::from_ymd_hm(2026, 8, 14, 8, 0); // Friday
    pour.duration = Some(16.0);

    let mut data = ProjectData {
        calendars: vec![six_day_week],
        tasks: vec![phase, pour],
        ..Default::default()
    };
    data.config.duration_unit = TimeUnit::Hour;
    data.config.calendar_mode = CalendarMode::TaskInherited;

    let options = SolveOptions { include_unchanged: true, ..Default::default() };
    let result = schedule(data, &options)?;
    for update in &result.updates {
        if let (Some(start), Some(end)) = (update.start_date, update.end_date) {
            println!("{}: {start} -> {end}", update.id);
        }
    }
    Ok(())
}
```

Output:

```text
pour: 2026-08-14 08:00 -> 2026-08-15 17:00
phase: 2026-08-14 08:00 -> 2026-08-15 17:00
```

`pour` works Friday and Saturday on the summary's six-day week. With the default mode it would wait for Monday.

## Resource calendars

In the default `Resource` mode each assignment works on its resource's calendar, and the task's dates follow its assignments. Give a resource a calendar through `ResourceData.calendar_id`. The example runs the same project in `Resource` and `Task` mode:

```rust
use plen_core::{
    schedule, AssignmentData, CalendarData, CalendarMode, DateTime, LinkData, LinkType,
    ProjectData, ResourceData, SolveOptions, TaskData, TimeUnit, Worktime,
};

fn project(mode: CalendarMode) -> ProjectData {
    let tue_sat = CalendarData {
        id: "tue-sat".into(),
        worktime: Some(Worktime {
            days: Some([false, false, true, true, true, true, true]),
            ..Default::default()
        }),
    };

    // `prepare` has no resources, so it runs on the global calendar
    // and ends Friday 17:00.
    let mut prepare = TaskData::new("prepare");
    prepare.start_date = DateTime::from_ymd_hm(2026, 8, 14, 8, 0);
    prepare.duration = Some(8.0);

    let mut inspect = TaskData::new("inspect");
    inspect.start_date = DateTime::from_ymd_hm(2026, 8, 14, 8, 0);
    inspect.duration = Some(16.0);

    let mut data = ProjectData {
        calendars: vec![tue_sat],
        tasks: vec![prepare, inspect],
        links: vec![LinkData {
            id: "l1".into(),
            source: "prepare".into(),
            target: "inspect".into(),
            link_type: LinkType::Fs,
            lag: 0.0,
            lag_unit: None,
        }],
        resources: vec![ResourceData {
            id: "dana".into(),
            capacity: None,
            calendar_id: Some("tue-sat".into()),
        }],
        assignments: vec![AssignmentData {
            id: Some("inspect:dana".into()),
            task: "inspect".into(),
            resource: "dana".into(),
            value: 1.0,
            offset: None,
            duration: None,
        }],
        ..Default::default()
    };
    data.config.duration_unit = TimeUnit::Hour;
    data.config.calendar_mode = mode;
    data
}

fn main() -> Result<(), Box<dyn std::error::Error>> {
    let options = SolveOptions { include_unchanged: true, ..Default::default() };
    for mode in [CalendarMode::Resource, CalendarMode::Task] {
        let result = schedule(project(mode), &options)?;
        for update in &result.updates {
            if let (Some(start), Some(end)) = (update.start_date, update.end_date) {
                println!("{mode:?} {}: {start} -> {end}", update.id);
            }
        }
    }
    Ok(())
}
```

Output:

```text
Resource prepare: 2026-08-14 08:00 -> 2026-08-14 17:00
Resource inspect: 2026-08-15 08:00 -> 2026-08-18 17:00
Task prepare: 2026-08-14 08:00 -> 2026-08-14 17:00
Task inspect: 2026-08-17 08:00 -> 2026-08-18 17:00
```

In `Resource` mode Dana works Saturday, so `inspect` starts right after `prepare` and runs Saturday and Tuesday. In `Task` mode her calendar is ignored and `inspect` waits for Monday on `"global"`.

The rules for picking an assignment's calendar:

- The resource has a calendar and the task doesn't: the resource's calendar.
- Both have one: their intersection. Give a task the `mornings` calendar and assign it to Dana, and the work runs Tuesday to Friday mornings only.
- The resource has none: the task's calendar.
- Summaries and milestones always use the task's calendar.

A task with several assignments on different calendars spans the **envelope** of its assignments. Each assignment starts at the first working time of its own calendar and runs the full duration there. The task ends when the last one ends. The reported `duration` stays the working time of each assignment, not the length of the envelope. Results don't include per-assignment dates.

Resource calendars also shape resource load: each assignment books work only on its own calendar. See [Resource load](<https://docs.dhtmlx.com/planning-engine/rust/resources-and-assignment/resource-load.md>).

## Flat time

Set `config.use_calendars` to `false` to schedule without working hours. Every calendar becomes 24/7, so a day of duration is 24 hours:

```rust
use plen_core::{schedule, DateTime, ProjectData, SolveOptions, TaskData};

fn main() -> Result<(), Box<dyn std::error::Error>> {
    let mut task = TaskData::new("burn-in");
    task.start_date = DateTime::from_ymd_hm(2026, 8, 14, 8, 0); // Friday
    task.duration = Some(2.0); // days

    let mut data = ProjectData {
        tasks: vec![task],
        ..Default::default()
    };
    data.config.use_calendars = false;

    let options = SolveOptions { include_unchanged: true, ..Default::default() };
    let result = schedule(data, &options)?;
    for update in &result.updates {
        if let (Some(start), Some(end)) = (update.start_date, update.end_date) {
            println!("{}: {start} -> {end}", update.id);
        }
    }
    Ok(())
}
```

Output:

```text
burn-in: 2026-08-14 08:00 -> 2026-08-16 08:00
```

With calendars on, the same task skips the weekend and ends on Tuesday at 08:00. The engine still validates calendar ids, but they all resolve to the same flat time, so you can toggle `use_calendars` without touching the rest of the data. In flat mode resource and assignment edits never move dates.

If you load data from dhtmlxGantt, send `use_calendars` explicitly. See [Import from dhtmlxGantt](<https://docs.dhtmlx.com/planning-engine/rust/how-to/import-from-dhtmlxgantt.md>).

## Explicit starts on non-working time

When an edit sets a start that falls on non-working time, the engine doesn't always snap it. A task **with no predecessor** keeps the exact start you gave it. Its end is computed forward on the working calendar, so the duration is still right. A task with a predecessor gets its start from the link instead.

```rust
use plen_core::{
    DateTime, Patch, Project, ProjectData, SchedulingChanges, SolveOptions, TaskData, TaskUpdate,
    TimeUnit,
};

fn main() -> Result<(), Box<dyn std::error::Error>> {
    let mut task = TaskData::new("deploy");
    task.start_date = DateTime::from_ymd_hm(2026, 8, 13, 8, 0); // Thursday
    task.duration = Some(4.0);

    let mut data = ProjectData {
        tasks: vec![task],
        ..Default::default()
    };
    data.config.duration_unit = TimeUnit::Hour;

    let mut project = Project::default();
    project.solve(Some(data), &SolveOptions::default())?;

    // The user drags the task onto Saturday 10:00.
    let saturday = DateTime::from_ymd_hm(2026, 8, 15, 10, 0).ok_or("invalid date")?;
    let mut update = TaskUpdate::new("deploy");
    update.start_date = Patch::Value(saturday);
    let mut changes = SchedulingChanges::default();
    changes.tasks.update.push(update);
    project.apply(&changes)?;

    let result = project.solve(None, &SolveOptions::default())?;
    for update in &result.updates {
        if let (Some(start), Some(end)) = (update.start_date, update.end_date) {
            println!("{}: {start} -> {end}", update.id);
        }
    }
    Ok(())
}
```

Output:

```text
deploy: 2026-08-15 10:00 -> 2026-08-17 12:00
```

The start stays on Saturday 10:00. The four hours of work run Monday 08:00-12:00. This applies to [`Project::apply`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/project/project.md#apply>) and [`preview`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/project/project.md#preview>), the calls behind drags in an editor.

This is by design. It's ported from the dhtmlxGantt planner, where the UI layer owns snapping. If your editor should only allow working-time starts, snap the date before you send the [`TaskUpdate`](<https://docs.dhtmlx.com/planning-engine/rust/api/core/changes/task-update.md>).
